So I want to see how many Not Started, In-Progress or Completed each person has.
Here you go.
=countifs([Assignee Column TItle]:[Assignee Column Title], "Assignee Name", Status:Status,"Not started")
Just replace Assignee Column Title with the title of your assignee column and replace assignee name with the name of your assignee. It can't be the email address but rather the display name.
Just change the status "Not Started" To whichever Status you want to replicate it for the other status' you are checking.
Thats Great Mike, so do I have to have a seperat formula for each status? or how can I show Mike Wilday 3 completed, 2 Not Started 1 In-Progess?
You could do something like this...
="Assignee Name: " + COUNTIFS(Assignee:Assignee, "Assignee Name", Status:Status, "Not started") + " Not Started; " + COUNTIFS(Assignee:Assignee, "Assignee Name", Status:Status, "In Progress") + " In Progress; " + COUNTIFS(Assignee:Assignee, "Assignee Name", Status:Status, "Complete") + " Complete;"
You would have to replace Assignee name and adjust your columns if they are different than Assignee and Status.
See screenshot for example.
Thank you it worked fine!
Awesome. Glad I could help.
Hey Mike, for some reason it wont pick up the rest of the Status only Not Started. What am I doing wrong here?
="Trinity Castle: " + COUNTIFS([Sales Rep]:[Sales Rep], "Trinity Castle", Status:Status, "Not started") + " Not Started; " + COUNTIFS([Sales Rep]:[Sales Rep], "Trinity Castle", Status:Status, " In-Progress") + " In-Progress; " + COUNTIFS([Sales Rep]:[Sales Rep], "Trinity Castle", Status:Status, "Complete") + " Complete;"
Trinity Castle: 1 Not Started; 0 In-Progress; 0 Complete;
Found the Typos, my bad they all work thanks again
Okay cool! Glad it's working!
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…