hello,
i am looking to find a way to do an average with the RYG balls.
ex: 2 green, 2 yellow, 2 red should have should show yellow ball for the overall project.
is this something possible?
thanks for your help
I can't help you with the method, but can I offer some thoughts?
When rolling up status (which isn't a great plan anyway), I always use the worse indicator rather than average.
e.g. if your project has 1 red indicator, it overrides 999 greens or yellows and I'd be reporting the overall status as red because you have an activity which isn't going to make it.
May be better to report on the number of reds, yellows and greens separately?
Not sure what metrics you are using or how you have defined RYG so happy to wind-my-neck-in if necessary!
I've created a dashboard with multiple graphs using data from the same report. I have added the report to the dashboard as well and set up the filter for use in the dashboard. Is this filter transferable to the graphs as well, given i can filter the report in the dashboard?
Dear Community, Can you please advise? I have a sheet where among other columns I have a column listing contacts "Champions" (multiple per cell) the other columns are for example: Countries (a list of 72) The list of Projects (approx 15) - I can add to that sheet, or I can create in a Helper Sheet. I haven't done that yet…
Looking for assistance again, I want to bring in the % complete from the Production sheet to the Schedule sheet, but once the % complete is 100 the data is moved to another sheet, so I would like to reference to check 1 sheet for percent complete and if it is not there check the second sheet. Schedule sheet: Pick Up Date…