how do i build a formula that gives me the actual date for today + 35 working days?
=Workday(Today(), 39)
will give you 39 working days from today.
https://help.smartsheet.com/function/workday
You need to put that in a date column and you need to understand that the date will change each day you load the sheeet. Today() will always refresh with the current day's date.
Hope that helps!
awesome thanks
You're welcome!
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…