How do I create a formula to subtract 30 business days from a certain start date?
I was trying to use =WORKDAY ([start date]13, -30) and it's not working. Note: the 13 is the row with the date I'm counting back from.
Thanks for your help!
That formula should work. I just tested it myself. Is the column you are putting the formula in formatted as a Date Column?
That's it! It was a text column - thank you so much!
It does work now but it's counting back calendar days and not work days - any ideas??
Hmm... I'm not sure. I just tested it again, and it was counting "workdays" (Monday - Friday). Putting in a start date of 6/29 gives me a result of 5/18.
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…