The NETDAYS between 5-Aug-2018 and 9-Aug-2018 is coming as 36530. I don't know what's happening - can anybody help?
=NETDAYS([Last Date Entered]4, Today4)
The same formula in another sheet is working absolutely fine.
Re-type your dates in. Looks like you accidentally put in 2118 instead of 2018 for the year, but since it's formatted as YY instead of YYYY, it looks right.
Good catch Javed!
Craig
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…