Is there are way to track the amount of time each stage of development takes?
What formula would I use and then, what chart?
Hi Michelle,
Yes, there is. It depends on how your solution is setup. Can you share the solution or upload some screenshots?
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done
Keep in mind... Tracking time in Smartsheet only works for days. Smartsheet cannot handle actual times (hours/minutes) without rather convoluted workarounds.
@Paul Newcome Is this still the case and l need a convoluted workaround to get how much time a generator was running?
Trying to calculate how many hours a generator run for, and for the cell to show as empty when there's no data in the cells. After reading a lot of posts came up with a formula but l can't figure out how to remove the "#INVALID VALUE" error, tried wrapping the formula in a "IF ERROR" but did not work.
This is my current formula, but there has to be something simpler and that allows for a cell to show as blank if both feeding cells are blank:
=VALUE(LEFT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Started]@row) - 1))) - VALUE(LEFT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) + (VALUE(RIGHT([Generator #2 Time Started]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) - VALUE(RIGHT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) / 60)
Screenshot of the sheet:
Thanks!
@Silvia Rangel That is correct. Smartsheet does not yet have built in time calculations. I will include a link at the bottom of this post to a thread that has numerous time based solutions in it.
As for the IFERROR, it should wrap around the entire formula like so...
=IFERROR(VALUE(LEFT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Started]@row) - 1))) - VALUE(LEFT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) + (VALUE(RIGHT([Generator #2 Time Started]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) - VALUE(RIGHT([Generator #2 Time Stopped]@row, (FIND(":", [Generator #2 Time Stopped]@row) - 1))) / 60), "")
@Paul Newcome Thanks! So, l realized l had a space between the end of the formula and the coma ( 60) , "") and this was giving me the error... Also, l tried the formulas in your ime based solutions post but none worked for what l am looking to do, at least for this sheet, as they worked for others! ☺
( 60)
@Silvia Rangel Glad you got that figured out. Are you still needing an overall formula? I would imagine a negative result for run time is not exactly accurate.
We set up a recurring Request for Update for each project when it starts. In the top row of the sheet, we use the feature to send an email at 8am every Friday morning. The past several months we have heard from various people each Friday they are missing one or more of these emails requesting an update. When we look at…
Hi all! I'm working on a column formula that will check whether the Column2ref cell in the current row is blank. If it is blank, the formula finds the maximum value in the ID column where the Trainer Name matches the Trainer Name cell value in the current row and the ID cell value is less than the ID cell value in the…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…