Does anyone see how to set the project date range in the project settings through the API?
I need to create a trigger that changes the dates that respond to the predecessors from one set of dates to another set of dates.
This had me curious. The api docs mention the 'ganttConfig' element, but when including that in a get sheet request, there is no additional data in the response:
http://smartsheet-platform.github.io/api-docs/#get-sheet
The only project settings I see from the API are 'lengthOfDay', 'workingDays' & 'nonWorkingDays'.
api@smartsheet.com maybe has the answer. Let me know what you figure out!
When you work with data in a spreadsheet or an AI client, what usually happens before it ends up in Smartsheet? Pick the closest one, and tell us how it really goes if it’s messier than the choices. It usually is. I copy and paste it over by hand I export a file and import it I clean it up in a spreadsheet first, then move…
At ENGAGE 2026, five customers showed what they’ve actually built with AI on top of Smartsheet. No roadmap slides, just working setups. Here’s the short version: Lilly Kinsale: One live changeover view, built with Claude. It saves roughly 30-35 minutes per core team member every day. Swampfox: AI proposes RAID log updates,…
I’m looking to use Linked Dropdown Columns within a CC blueprint template My setup is that each provisioned project gets its own workspace containing: Project Plan Team Roster I want a dropdown column in the Project Plan to be linked to specific column in that same project's Team Roster. For example: Project A Project Plan…