I cannot get this formula to work. Any suggestions?
=IF([% Complete]1=0%,"Not Started",IF([% Complete]1=100%,"Completed","In Progress"))
Hi Scott,
Smartsheet looks at the numbers in a column formatted for percentage (for example, a % Complete column) as values between 0 and 1. Use decimal values (examples: 0.25 for 25%, 0.5 for 50%) to get the correct comparison, as opposed to whole numbers.
Try this.
=IF([% Complete]@row = 0; "Not Started"; IF([% Complete]@row = 1; "Completed"; "In Progress"))
The same version but with the below changes for your and others convenience.
=IF([% Complete]@row = 0, "Not Started", IF([% Complete]@row = 1, "Completed", "In Progress"))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did it work?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I've created a dashboard with multiple graphs using data from the same report. I have added the report to the dashboard as well and set up the filter for use in the dashboard. Is this filter transferable to the graphs as well, given i can filter the report in the dashboard?
Dear Community, Can you please advise? I have a sheet where among other columns I have a column listing contacts "Champions" (multiple per cell) the other columns are for example: Countries (a list of 72) The list of Projects (approx 15) - I can add to that sheet, or I can create in a Helper Sheet. I haven't done that yet…
Looking for assistance again, I want to bring in the % complete from the Production sheet to the Schedule sheet, but once the % complete is 100 the data is moved to another sheet, so I would like to reference to check 1 sheet for percent complete and if it is not there check the second sheet. Schedule sheet: Pick Up Date…