Hi!
I have two columns. One if the Due Date and the other is the Completed Date. I would like to set-up an equation where it counts the number of times an item was completed late (after the due date). Is this possible? If yes, what is the equation?
Hmmm. I swear I know a better way of doing this, but I am having trouble getting anything to work. To do this quickly, you could create a helper column and use the following IF statement =IF([Completed Date]@row > [Due Date]@row, "late")
That will write the word late in the row... then you could do a simple... =Countifs([Helper Column]:[Helper Column], "late")
You could do this with the followting equation:
=IF([Completed Date]3 > [Due Date]3, 1, "")
This will put a 1 in the column if the Completed Date was after the Due Date. Then sum the column.
Here is an example sheet https://app.smartsheet.com/b/publish?EQBCT=d3c78d81b9424434a84055dfa1e2f28d
Comparing two (or more) columns for a count at the row level without a helper column is possible with an absurd amount of nested COLLECT functions which also happens to be rather inflexible and easily broken.
I have tested and dug through the forums here and tested some more, and the best thing by far I personally have found has been to use a helper column to compare the cells at the row level and then count the helper column.
If you can find a different way, I'm all ears. Adding extra stuff in after a sheet has been in use enough to have a few thousand rows is rather tiresome.
Not sure what to title this, because it's not really Cell Linking the way we talk about it with Smartsheet… I have two sheets, Project Sheet has project rows and a column that lists animal species impacted (currently text, but could be multi-dropdown if that helps?). The second sheet (Species Sheet) has "more info" on…
I am trying to find a way to look at text fields and automatically remove date and time stamps plus employee names. Any recommendations on identifying and removing text strings that meet the below formats: YYYY-MM-DD HH:MM:SS.SSSSSSS ####### [Employee Name] YYYY-MM-DD HH:MM:SS.SSSSSSS ####### [Employee Name] We have a…
Hi All, I'm working on a formula that is evaluating three columns of data: 1) EOY Target Weighted MWh 2) Forecast Weighted MWh 3) Increase/Decrease (to determine if the goal for the year is to increase or decrease the MWh) Here is my current formula: =IF([Forecast Weighted MWh]@row = [EOY Target Weighted MWh]@row, "On…