Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
Hi!
I have two columns. One if the Due Date and the other is the Completed Date. I would like to set-up an equation where it counts the number of times an item was completed late (after the due date). Is this possible? If yes, what is the equation?
Hmmm. I swear I know a better way of doing this, but I am having trouble getting anything to work. To do this quickly, you could create a helper column and use the following IF statement =IF([Completed Date]@row > [Due Date]@row, "late")
That will write the word late in the row... then you could do a simple... =Countifs([Helper Column]:[Helper Column], "late")
You could do this with the followting equation:
=IF([Completed Date]3 > [Due Date]3, 1, "")
This will put a 1 in the column if the Completed Date was after the Due Date. Then sum the column.
Here is an example sheet https://app.smartsheet.com/b/publish?EQBCT=d3c78d81b9424434a84055dfa1e2f28d
Comparing two (or more) columns for a count at the row level without a helper column is possible with an absurd amount of nested COLLECT functions which also happens to be rather inflexible and easily broken.
I have tested and dug through the forums here and tested some more, and the best thing by far I personally have found has been to use a helper column to compare the cells at the row level and then count the helper column.
If you can find a different way, I'm all ears. Adding extra stuff in after a sheet has been in use enough to have a few thousand rows is rather tiresome.
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…