Greetings,
Does anyone know if there is a formula to automate RYG based on Variance? I am trying to track budget (not dates). I would like to show Red balls when a task is over budget.
Any ideas on the formula?
Thank you!
I think there are a variety of ways to accomplish what you are trying to do. Are you trying to figure variance on a row by row basis or by sum total of the entire budget for the sheet like for a roll-up?
Here are two examples of formulas you could use:
Row by Row: =IF(Actual@row > Budget@row, "Red", "Green")
Sum of Columns: =IF(SUM(Actual:Actual) > SUM(Budget:Budget), "Red", "Green")
You can see both of them at work in my screenshot below. Right click on it to open it in a new window. You can see the item flagging red, while the overall budget is still on track. Hope that helps!
Did this solution work for you?
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…