=IF(Status8 = "Complete", "Blue", IF([Due Date]8 < Today8, "Red", IF([Due Date]8 = Today8, "Yellow", IF([Due Date]8 > Today8, "Green"))))
Very new at this, but I can't see the problem...
Try:
=IF(Status8 = "Complete", "Blue", IF([Due Date]8 < Today(), "Red", IF([Due Date]8 = Today(), "Yellow", IF([Due Date]8 > Today(), "Green"))))
edit: I'd also change to @row cell references. It'll make easier to copy.
=IF(Status@row = "Complete", "Blue", IF([Due Date]@row< Today(), "Red", IF([Due Date]@row= Today(), "Yellow", IF([Due Date]@row> Today(), "Green"))))
I've created a dashboard with multiple graphs using data from the same report. I have added the report to the dashboard as well and set up the filter for use in the dashboard. Is this filter transferable to the graphs as well, given i can filter the report in the dashboard?
Dear Community, Can you please advise? I have a sheet where among other columns I have a column listing contacts "Champions" (multiple per cell) the other columns are for example: Countries (a list of 72) The list of Projects (approx 15) - I can add to that sheet, or I can create in a Helper Sheet. I haven't done that yet…
Looking for assistance again, I want to bring in the % complete from the Production sheet to the Schedule sheet, but once the % complete is 100 the data is moved to another sheet, so I would like to reference to check 1 sheet for percent complete and if it is not there check the second sheet. Schedule sheet: Pick Up Date…