Hi to all,
I need to add a % Planned to my plan. I used a formula but it didn't work.
Attached you have a screenshot of my plan with the formula and the dates columns.
Thanks for your advice!!
Adelina
Hi Adelena. The primary issue I see with your formula is how you are referencing the column names in it. And that you are referencing any row numbers. When referencing a column name with spaces always wrap your column name in brackets like this... [End Date]
You also need to either reference a specific row number after the column name or use smartsheets @row trick to reference the current row. It should looks like this... [End Date]3 --- which will reference row 3. OR [End Date]@row to reference the current row you are in.
Regarding your formula it should look something more like this...
=Round(IF(Today() < [Start Date]@row, 0, IF(...
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…