Is there a way in data matrix to do a formula to count the the number of lines with a due date today to 30 days out? I am trying to see item that will hit in the future.
Can you share a screenshot so we can see what you are referring to?
You can do a Countif of row that are greater than today().
=Countifs([Date Row Title]:[Date Row Title], >Today())
If you need a cross sheet reference you can do that too. After entering =Countifs( click on the little link that reference data from another sheet in the help box that appears..
I cant seem to have that work how i want. but here is screen shot
it still doesnt pull anything with that formula.
It actually looks like you're trying to sum data there. That is different than count...
Here is the sumifs formula... If you're using cross-sheet references you will need to reference one column at a time. You'll have to create each cross sheet column individually.
=Sumifs({Value column to sum from Cross Sheet}, {Date Column from Cross Sheet Reference}, >Today(30))
https://help.smartsheet.com/function/sumifs
And as I read your comments, I think I might have that formula a little bit off.
=Sumifs({Value column to sum from Cross Sheet}, {Date Column from Cross Sheet Reference}, <Today(30), {Add a new refrence to the Date column}, >Today())
That will sum every row that has a due date that is less than 30days from today, and is greater than today. Essentially the next 30 days.
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…