Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
Good evening,
I will try and explain this without messing up
Thank you
We need something similar. I would love to see what other users are doing. Currently we have to manually update the percent column to 100% each time a task is complete.
We have tried the predecessor option as well, but it limited some of our other features.
Hi,
Are the task always completed in the same order?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hi Yes
They are always completed in the same order but sometimes some tasks are not needed.
Ok.
Try something like the below formula to start.
=IF(F1 = 1; 1; IF(Admin@row = 1; 1; IF(Unload@row = 1; 0,8; IF(Weld@row = 1; 0,6; IF([Fit Up]@row = 1; 0,4; IF(Python@row = 1; 0,2))))))
The same version but with the below changes for your and others convenience.
=IF(F1 = 1, 1, IF(Admin@row = 1, 1, IF(Unload@row = 1, 0.8, IF(Weld@row = 1, 0.6, IF([Fit Up]@row = 1, 0.4, IF(Python@row = 1, 0.2))))))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Hope that helps!
Andrée
Hi Julie,
Does the below formula help you or do you have some other requirements?
HI Andree
Trying now
Happy to help!
Let me know how it goes!
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…