Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
The posts in this section are historical and no longer monitored for accuracy. If this discussion interests you and you'd like to join in, please visit the active Community to post and engage.
I'm entering 2 hrs in duration, but over in the gant chartt, it shows 2 days. advice on how to enter/view this corretly?
Carla,
Something looks odd.
Are Dependencies set?
Your "Start By" date shows 11/18 and your "Finish Date" shows 11/19 - which matches the Gantt chart.
Either Dependencies are not set or they are and the system is looking at the wrong or no Duration column.
Hope this helps
Craig
thanks Craig.
When I change the # of days (d), weeks (w), or minutes (m), the dates and Gantt Chart respond correctly, However, when I change it in hours (h), the dates and gantt chart respond as if it were days.
Carla, would you please share the sheet with me as an Admin so I can take a look?
travis.hannon@smartsheet.com
Thanks!
Thanks for sharing the sheet! In your project settings, you have your Length of Day set to 1 hour. When your day is 1 hour long, 2 hours will be two days.
Try changing your length of day to 8 hours (or however long your workday is).
I would not have guessed that one.
Awesome, Travis! Typo, should have been a 10...
Thanks so much!