I have my start date auto filled when I enter information into a new row. I now want my due date to auto fill to 7 work days after the start date. How do I do this?
Right now I have this for row 5
=WORKDAY([Start Date]5 + 7)
Any help would be great!
You can reference the formula for workdays here: https://help.smartsheet.com/function/workday
You were close. =Workday([Start Date]5, 7)
You can also use @row instead of calling the row number to ensure your date is always accurate to the row its on.
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…