I'm looking for a formula that would let me update the status column when the %Complete has a value entered. It should read if 0% is entered Status would be not started; if a value of 1-99% is entered then it is in "Progress" in the status column. If the % Complete value is 100% then the status column would show "Complete" in the status column.
=IF([% Complete]@row = 0, "Not started", If([% Complete]@row < 1, "In Progress", IF([% Complete]@row = 1, "Complete")))
Try that formula in the Status column.
That worked.. Thanks!
You're welcome. Great Job.
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…