I am attempting to do the following.
If the "Completed" column has a check, in the checkbox, I would like the % Complete column to read 100%
Here is the formula I thought would work using task 4.of the project.
=IF(Completed4 = "Complete", "100%")
Found my error
The formula should have been
=IF(Completed4 = "true", "100%"
Here is another option.
=IF(Completed@row = 1, 1)
You will need to format your % complete column as a % but then it will load the actual % rather than text.
What if there are multiple status' that equal 100%? what would the formula be for that?
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…