I need to add multiple columns that allows us to input the "on site date", - "Manufacturer Lead time" - "Drawing Approval" = Drawing start Date.
Screenshot as below.
Appreciate any help to solve this issue.
Regards Daniel
Hi Daniel,
Not sure this is what you wanted.
Try something like this.
=[On Site Date]@row- [Manufacturer Lead Time]@row- [Drawing Approval]@row
The same version but with the below changes for your and others convenience.
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Let me know if I misunderstood your need!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hello Andree
thanks for this, doesnt seem to work but this could be down to the column properties.
on site date = Date/time
Manufacturing Lead time = ???
Drawing approval = ???
Drawing start date = Date/time
sorry new to smartsheet and formulas.
When dependencies are enabled only one start date, one finish date, and one duration column can be used. To have multiple durations factored in to a task, you will need to break each part down into a child row of the overall task.
If you are wanting to keep everything in one row, you will need to convert your durations into a number of days and then use those for your calculations.
For example... If your first duration is 2w and your second is 4w, you would need to convert them to 14 and 28 respectively and then use the 14 and 28 to calculate your dates.
Hello Paul
thanks for this, i understood what you are saying so the last paragraph is something i could use, but how would this be reflected in column required and formulas to make this work.
This works now perfectly, thanks for all your help.
Glad you were able to get it working. Happy to help!
Happy to help!
I saw that Paul answered already and that you've got it working!!
Let me know if I can help with anything else!
Andrée
I've created a dashboard with multiple graphs using data from the same report. I have added the report to the dashboard as well and set up the filter for use in the dashboard. Is this filter transferable to the graphs as well, given i can filter the report in the dashboard?
Dear Community, Can you please advise? I have a sheet where among other columns I have a column listing contacts "Champions" (multiple per cell) the other columns are for example: Countries (a list of 72) The list of Projects (approx 15) - I can add to that sheet, or I can create in a Helper Sheet. I haven't done that yet…
Looking for assistance again, I want to bring in the % complete from the Production sheet to the Schedule sheet, but once the % complete is 100 the data is moved to another sheet, so I would like to reference to check 1 sheet for percent complete and if it is not there check the second sheet. Schedule sheet: Pick Up Date…