I have tried searching and figuring out what my formula should be, but I just can't get it. I want my flag to be red when there are 3 days or less to due date. Frustrated. See screenshot.
Try something like this...
=IF(TODAY(3) >= [Due Date]@row, 1)
To get it to ignore the flag once the row has been checked as complete, you would use this...
=IF(AND(Complete@row = 0, TODAY(3) >= [Due Date]@row), 1)
That works perfectly! Thank you so very much!
Happy to help!
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…