I have tried searching and figuring out what my formula should be, but I just can't get it. I want my flag to be red when there are 3 days or less to due date. Frustrated. See screenshot.
Try something like this...
=IF(TODAY(3) >= [Due Date]@row, 1)
To get it to ignore the flag once the row has been checked as complete, you would use this...
=IF(AND(Complete@row = 0, TODAY(3) >= [Due Date]@row), 1)
That works perfectly! Thank you so very much!
Happy to help!
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…