I have tried searching and figuring out what my formula should be, but I just can't get it. I want my flag to be red when there are 3 days or less to due date. Frustrated. See screenshot.
Try something like this...
=IF(TODAY(3) >= [Due Date]@row, 1)
To get it to ignore the flag once the row has been checked as complete, you would use this...
=IF(AND(Complete@row = 0, TODAY(3) >= [Due Date]@row), 1)
That works perfectly! Thank you so very much!
Happy to help!
Hi all, reaching out to see if of you have ideas; I'm hoping this makes sense: I'm having some trouble getting my formulas to pull data in correctly. I currently have a sheet (primary data) where I have data in rows where each row is a single project, with columns identifying persons, $ values, unique project identifier,…
Hello, I have a workflow where, when a team member checks a checkbox, Smartsheet automatically sends an email to themselves containing merge fields that are used as a customer email draft. The challenge is that this activity typically happens on a deadline day, and a team member may need to generate 30 or more of these…
I have a sheet with 5000 rows and 30 columns. with 4 columns of them are formular columns. How can i reach this limit for 25000000 formular cells reference? How can i enlarge this limit? I need those formular to link some data from another sheet as there is also Max cells limit for one sheet. How can I join those data…