Here is my formula. It is in a project plan:
=IF(TODAY() > [End date]1, [% Complete]1 < 100%, "At Risk", "On Time")
Hi Andy,
At first glance, it looks like the percent complete is wrong. It's written as 1 for 100%.
Try this.
=IF(TODAY() > [End date]1, [% Complete]1 < 1, "At Risk", "On Time")
Have a fantastic weekend!
Did it work?
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
It also looks like you might be wanting to make sure both of those stipulations apply...
Try this... IF(And(TODAY() > [End date]1, [% Complete]1 < 1),"At Risk", "On Time")
I had tried that earlier and it didn't so I just tried again. Now error is incomplete argument set
That worked! Thanks so much Mike. I tried the "and" earlier and it wasn't working. Then I read that you can list "if" conditions (and it's called nesting) so I tried going with that.
Thanks so much!!!
You're welcome! Glad I could be of help to you.
Happy to help!
I saw that Mike answered already, and it's solved now!
Let me know if I can help with anything else!
Andrée
How do I see who submitted a form for a specific sheet?
Hi, I have a Gantt covering 500+ rows of events past and planned. I use it to predict and track values around these events. Using helper columns to identify the current week, I get an email report on a Monday that tells me the upcoming events in the current week (7 days) and their values. Currently if an event spans…
Hi Smartsheet Community, I'm working on an action management system where users create sub-actions through a Smartsheet Form. The requirement is simple: a sub-action's due date must be earlier than or equal to its parent action's due date. For example, if the parent action is due on June 30, 2027, users should not be able…