Here is my formula. It is in a project plan:
=IF(TODAY() > [End date]1, [% Complete]1 < 100%, "At Risk", "On Time")
Hi Andy,
At first glance, it looks like the percent complete is wrong. It's written as 1 for 100%.
Try this.
=IF(TODAY() > [End date]1, [% Complete]1 < 1, "At Risk", "On Time")
Have a fantastic weekend!
Did it work?
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
It also looks like you might be wanting to make sure both of those stipulations apply...
Try this... IF(And(TODAY() > [End date]1, [% Complete]1 < 1),"At Risk", "On Time")
I had tried that earlier and it didn't so I just tried again. Now error is incomplete argument set
That worked! Thanks so much Mike. I tried the "and" earlier and it wasn't working. Then I read that you can list "if" conditions (and it's called nesting) so I tried going with that.
Thanks so much!!!
You're welcome! Glad I could be of help to you.
Happy to help!
I saw that Mike answered already, and it's solved now!
Let me know if I can help with anything else!
Andrée
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…