Hello!
I'm trying to setup a project plan for when a task is marked 'complete' it auto-fills the 'Finish Date' column. Would I use an If, then formula? If so, what would that formula look like?
Thanks!
Crystal
Hi Crystal, this functionality is not currently available without using a third party tool like Zapier. We reverse-engineered our process to have the person enter a date and then have the status update accordingly.
Thanks, Mike! This is helpful. I'll try that approach.
Sounds good. Let me know if you have any questions! We created an Actual Start and an Actual finish date field to measure if the task was in progress or complete and changed the dropdown field with an IF function based on the dates being populated.
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…