Hey All!
I have a question for the community that i'm having trouble figuring out to return a certain value to another sheet based on criteria. The pic I attached shows a project budget setup and I am wanting to pull data from the Budget cell based on the Job ID and the Cost Category. I'm not sure if it is a Index - Match function or a combination of Vlookup / Hlookup but any help is greatly appreciated!
Hi Ryan,
I'd recommend using a VLOOKUP or INDEX/MATCH combination.
Can you describe your process in more detail and maybe share the sheet(s), copies of the sheet(s)? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Andree,
I have a another sheet that needs to pull the cell value for Materials in the Budget column but based on the Job ID because there will be about 30 different project budgets all in the same sheet. Does that help? I'm going to make a copy of the sheet and share it with you.
Thanks!
That helps!
I'll take a look and get back to you!
Hi everyone! I have a list of report dates that I want to be notified on, but am having trouble getting this set up. My thought process was to create a column with =TODAY() in the first cell, and then set up automations to be alerted when "Today" equals the "Report Date". My issue is that two are different formats. The…
Currently below is what Smartsheet allows for Group management. In our organization, this is very restrictive as it only allows 3 people to manage groups that required a lot of maintenance. Allows Group Admins this ability would make it much more flexible for large organizations who have multiple individuals with the…
Hi All i am trying to determine the stage that a project should have readhed by today, based on a series of milestone dates across the row however, in this particular example i am getting #invalid operation which may be due to the blanks. they are blanks because they currently have no date which is probably a flaw in the…