I'm trying to report down the same date as my parent date. Of course this simple formula is not giving me the results I need.
I need the parent date for each job
You do not need a reference in the PARENT formula. Absent a reference, it will use the current row.
Hi Gina,
Try this.
=PARENT()
Did it work?
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
A little explanation as to Andree's correct solution.
Your formula of
=PARENT(Week3)
is saying to look at the parent of that cell. Week3. If you look at the parent of that cell, you will see that it is blank.
To reference the cell that the formula is residing in
=PARENT(this cell that the formula is in)
you would just leave out the cell reference.
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…