Hello,
I added the new roundup formula to my sheet and this cause all of my reports that reference this column to show up as #unparseable only on the report. This shows as a value on the main sheet. To make this worse any other formula on this sheet shows up as #blocked until this is removed
Hi,
Don't you see an error in the sheet at all?
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Once I changed the roundup formula back to round the errors were cleared. I had submitted a ticket #03576186 and have not gotten an answer.
the issue was not on any of the sheets they were working. On the reports that reference those sheets any equation that had Roundup would show as unparseable and any equation that referenced that cell would show as blocked. this is what cause the confusion. I could see the values on the sheet but on the report they showed as errors. There must be a problem with the new roundup/ rounddown formula.
Ok.
Let's wait for what the Smartsheet Support Team says.
I have an Action Log and in the log we have a column that identifies the different projects our team leads. There is also a Workstream column, which identifies what workstream is responsible for getting the answer. There can be more than one answer, so we have a dropdown and if multiple workstreams are responsible for the…
So here what I'm trying, I have multiple solution and status for all. Trying to get the total net worth value of order based on solution + individual status. Let's say I want to capture the total revenue for Centralised Inventory with all different status as below: I tried with Sumifs but it's not calculating all values.…
I would love some help troubleshooting a column link issue between two sheets used for department metric scorecards. Sheet 1 (source sheet) is the metric submission sheet where metric owners report quarterly data. Sheet 2 (target sheet) is the scorecard that shows quarterly goals and actuals, with a status symbol for each…