I'm trying to enter a formula in a date field which is 10 days earlier than the date in another field. I read that I can perform calculations on date fields (https://help.smartsheet.com/articles/2477601-use-formulas-perform-calculations-dates) and reference another cell in the formula (https://help.smartsheet.com/articles/2476816-create-cell-column-reference-formula).
My formula is
=[Start Date]42-10
because I want the date that is 10 days earlier than the cell in row 42 of the "Start Date" column.
However, when I enter this formula in the cell and hit Enter, all I see is the formula itself. See attached screenshot. What am I doing wrong?
If the date column is assigned to either the start or end date columns and you have dependencies enabled in your project settings you cannot have a formula on it. These fields are calculated my SmartSheet based on the dependencies.
The project settings are accessible in the Gantt View via the cog (settings) icon under the Share button.
Frank is correct. It seems as if you have your dependencies enabled and are using that column as one of your project columns. You have a few options...
1. Disable dependencies in the Project Settings.
2. Create another column for the calculated dates.
3. Select a different column in your Project Settings.
4. Add lag/lead time if establishing predecessors.
Thank you, Frank and Paul!
Happy to help!
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…