Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
I am trying to automate the RYGGrey ball status column, based on two date columns ([Start] and [Finish]) and 2 check columns ([Task Started] and [Task Completed]). Having trouble getting started and follow the right syntax. Here are my conditions I am trying to meet.
TIA for your help.
Grey
OR
Red
Yellow
Green
See if this works for you.
=IF([Task Completed]@row = 0, IF(TODAY() < Finish@row, "Grey", IF(TODAY() > Finish@row, "Yellow", "Red"), IF([Task Started]@row = 0, IF(TODAY() < Start@row, "Grey", IF(TODAY() > Start@row, "Yellow", "Red")), "Green")), "Green")
Thanks, Paul. I put your formula into my sheet and go #INCORRECT ARGUMENT SET. Not sure how to proceed since I am new at building complex formula's. Any suggestions?
Screen shot of sheet.
=IF([Task Completed]@row = 0, IF(TODAY() < Finish@row, "Grey", IF(TODAY() = Finish@row, "Yellow", IF(TODAY() > Finish@row, "Red", IF([Task Started]@row = 0, IF(TODAY() < Start@row, "Grey", IF(TODAY() = Start@row, "Yellow", IF(TODAY() > Start@row, "Red"))), IF(TODAY() <= Start@row, "Green"))))), IF(TODAY() <= Start@row, "Green"))
.
If this doesn't work, I am going to need to do some additional testing. Let me know how it goes.
Thanks again, Paul. It works but I realize we did not account for if the Start and Finish are past today but the task has been started and completed (see row 3 and 4 of screen shot). The Status is just blank. How do we incorporate this to be yellow?
Sorry. I'm not sure I follow.
If both boxes are checked and the start and finish are both in the past, you want "Yellow"? This will eventually change ALL completed tasks to yellow as you pass each of the dates. So even if you have a task completed (for example) one year in advance, in one year and one day, that color will then change to yellow.
Hello, I have a workflow where, when a team member checks a checkbox, Smartsheet automatically sends an email to themselves containing merge fields that are used as a customer email draft. The challenge is that this activity typically happens on a deadline day, and a team member may need to generate 30 or more of these…
Hi all, reaching out to see if of you have ideas; I'm hoping this makes sense: I'm having some trouble getting my formulas to pull data in correctly. I currently have a sheet (primary data) where I have data in rows where each row is a single project, with columns identifying persons, $ values, unique project identifier,…
I have #'s that pull from each project into each sheet's - sheet summary. Those then get pulled into a sheet summary report. They are currently grouped by what channel they are in. Each column gives a total sum. I was asked to see if we can combine the total sum into one number, so it shows how many total SKU's are being…