I would like the column "Done" to be checked automatically if the % Complete is changed to 100%. I am using the formula below which is not working:
=IF([% Complete]3 = "100%", 1)
Any suggestions?
If your % Complete column is formatted to be a percentage, you will need to replace "100%" with 1 (no quotes).
=IF([% Complete]@row= 1, 1)
thank you so much!!! it worked
Happy to help!
Smartsheet stores percentages as a fraction of 1, so
100% = 1
75% = 0.75
50% = 0.5
25% = 0.25
0% = 0
and everything in between.
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…