I would like the column "Done" to be checked automatically if the % Complete is changed to 100%. I am using the formula below which is not working:
=IF([% Complete]3 = "100%", 1)
Any suggestions?
If your % Complete column is formatted to be a percentage, you will need to replace "100%" with 1 (no quotes).
=IF([% Complete]@row= 1, 1)
thank you so much!!! it worked
Happy to help!
Smartsheet stores percentages as a fraction of 1, so
100% = 1
75% = 0.75
50% = 0.5
25% = 0.25
0% = 0
and everything in between.
I am using the new "linked" column for a dropdown on my sheet. Is there any way to sort the dropdown options? I have sorted them on my source sheet, however it doesn't update in the dropdown.
I am building out my sheet summary from a schedule. I have a Parent Row column and all of my parent rows have a checkbox. I want a formula that looks at the first checkbox and looks at the status. If status is Complete, that summary field would then indicate that the Project is in Definition. If the status is In Progress…
I'm trying to create a formula that requires the account# to be 10 digits. I've tried the formulas that I've generated, and they all return an error. This information is tied to a form that requires the account. Help please.