Hi - I'm trying to add 6 months to the day to a date referenced in another field. It is basically a date of execution and plus 6 months a review date. How is this possible? Adding the number of days gets me close, but not exact.
Thanks!
Try something like the below. We first use a DATE function to simply add 6 to the month. Then we use an IFERROR function to produce a different date if the month + 6 is more than 12. The different date would simply be subtracting 6 months and then adding 1 to the year.
=IFERROR(DATE(YEAR([Execution Date]@row), MONTH([Execution Date]@row) + 6, DAY([Execution Date]@row)), DATE(YEAR([Execution Date]@row) + 1, MONTH([Execution Date]@row) - 6, DAY([Execution Date]@row)))
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…