I'm having trouble with creating a formula that flags my status column as "overdue" when I'm not at 100% complete and past a tasks end date for that line. i've read a lot of the other posts but none of the formulas seem to apply or work when I input them. Please let me know your thoughts. Thank you!
Give this a whirl...
=IF([% Complete]@row = 1, "Complete", IF([End Date]@row < TODAY(), "Overdue", IF([% Complete]@row = 0, "Pending", "In Progress")))
The dashboard previously contained 16 widgets, and I have confirmed that the widgets still exist in the backend. However, when I open the dashboard, nothing is displayed, and I am unable to enter Edit Mode or access the widgets/data sources. I have already confirmed the following: I am the owner of the dashboard and have…
I have an end date column and want to add 30 days to that for a new column that shows due date. How do I add 30 days to a date automatically?
Why is it so convoluted now! I eventually figured out the changes and ended up with a sheet that Smartsheet completely reorganised the rows and the sheet is now useless to me as it is not in a logical order for me to easily restore to its original layout. This is not an "improvement"! It was far easier to upload data…