Hi,
after the project was created some columns were not correctly set, is there any way to ask contorl center to rebuild the reporting sheet ?
Hi Etienne,
There's a feature called Global Updates that is built just for this!
For sheets- https://help.smartsheet.com/articles/2476706-smartsheet-control-center-make-global-updates
For reports- https://help.smartsheet.com/articles/2479386-smartsheet-control-center-global-updates-reports
For dashboards- https://help.smartsheet.com/articles/2479391-control-center-global-updates-dashboards
If I only want to copy certain columns say once a week (upload workflow) from Excel into Smartsheet to replace the previous week's data, but I don't have the option to add a Unique row ID in the Source file, is it possible to do this Data shuttle copying of only certain columns from Excel into the smartsheet data shuttle…
Hello, I'd like to do the workflow as mentioned in the title above, but I'm limited in a couple of aspects: I'm unable to add unique row IDs in my source data file (which I'm importing/uploading from Excel), does this limit my ability to use Merge (add & update) Data Shuttle workflow? If I use the Replace workflow of Data…
Hello, Is it possible to do a smartsheet data shuttle replace target sheet rows by only replacing certain columns in a row and keeping other columns in a row intact? Essentially, I want to be doing a weekly replacement of the target sheet (ie. not updating consecutive data sets) by Data Shuttle upload of an Excel sheet? I…