We need more control over scheduling to make this product useful. I just had an issue where after 200 some activities where entered with dates and it was realized it should be based on a 7 day week not 5 day. Switching to a 7 day changed all the end dates. In my view I should have been given the choice of adjusting the end date or the duration. I now have to go back and change all the dates by hand.
Interesting point. I wonder if there is a way to make the finish date the primary date instead of the beginning date.