Hello,
I dont find way how I can make that in Gantt view show two dates - planned finish date and actual finish date - but I need it show in one row?
The Gantt chart can only show one start and one finish date, so you cant view a baseline in the Gantt. You can have this information in your grid view and use formulas to show the difference between your actual and planned dates.