Hello
I have a task made up of multiple intervals, can smartsheet include these in the tasks/gannt?
Example - task 'a' - start 28/4, finish 29/4, start (1) 2/5, finish (1) 4/5, start (2) 6/5, finish (2) 13/5
Thanks
Alan Russell
I am looking for a way to enter recurring (weekly/monthly) tasks so users don't have to enter them all manually.
Hi Alan,
off the top of my head I would think the parent-child relationship of sub-tasks might serve your need.
Example: