Hello SmartSheet community,
I would like to add bankholidays under a "depencies disabled" mode.
It this possible ?
I take it that with a "dependency enabled" mode, that's already feasible.
https://help.smartsheet.com/articles/516392-defining-working-non-working-holidays-on-a-project-sheet
Best
Hello,
At this time, dependancies must be enabled in order for non-working days or holidays to be excluded in the duration calculation.
As a workaround, you could create a formula using the NETWORKDAY function to calculate the number of days between two dates, adding 1 day to the result if the start date is a non-working day.
The NETWORKDAY function allows you to enter the dates you would like to exclude. More information on this function can be found here: https://help.smartsheet.com/function/networkday
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.
I have reproduced the following behavior in a validated Smartsheet application. User permission: Editor (not Admin) Row status: Locked (confirmed via row menu displaying "Unlock Row") Text, Date, Contact List, and Checkbox columns cannot be modified. Dropdown List columns remain editable. Selecting a new dropdown value and…