Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
I am attempting to do the following.
If the "Completed" column has a check, in the checkbox, I would like the % Complete column to read 100%
Here is the formula I thought would work using task 4.of the project.
=IF(Completed4 = "Complete", "100%")
Found my error
The formula should have been
=IF(Completed4 = "true", "100%"
Here is another option.
=IF(Completed@row = 1, 1)
You will need to format your % complete column as a % but then it will load the actual % rather than text.
What if there are multiple status' that equal 100%? what would the formula be for that?
Hi all, reaching out to see if of you have ideas; I'm hoping this makes sense: I'm having some trouble getting my formulas to pull data in correctly. I currently have a sheet (primary data) where I have data in rows where each row is a single project, with columns identifying persons, $ values, unique project identifier,…
Hello, I have a workflow where, when a team member checks a checkbox, Smartsheet automatically sends an email to themselves containing merge fields that are used as a customer email draft. The challenge is that this activity typically happens on a deadline day, and a team member may need to generate 30 or more of these…
I have a sheet with 5000 rows and 30 columns. with 4 columns of them are formular columns. How can i reach this limit for 25000000 formular cells reference? How can i enlarge this limit? I need those formular to link some data from another sheet as there is also Max cells limit for one sheet. How can I join those data…