I have tried searching and figuring out what my formula should be, but I just can't get it. I want my flag to be red when there are 3 days or less to due date. Frustrated. See screenshot.
Try something like this...
=IF(TODAY(3) >= [Due Date]@row, 1)
To get it to ignore the flag once the row has been checked as complete, you would use this...
=IF(AND(Complete@row = 0, TODAY(3) >= [Due Date]@row), 1)
That works perfectly! Thank you so very much!
Happy to help!
Hello, I have a workflow where, when a team member checks a checkbox, Smartsheet automatically sends an email to themselves containing merge fields that are used as a customer email draft. The challenge is that this activity typically happens on a deadline day, and a team member may need to generate 30 or more of these…
Hi all, reaching out to see if of you have ideas; I'm hoping this makes sense: I'm having some trouble getting my formulas to pull data in correctly. I currently have a sheet (primary data) where I have data in rows where each row is a single project, with columns identifying persons, $ values, unique project identifier,…
I have #'s that pull from each project into each sheet's - sheet summary. Those then get pulled into a sheet summary report. They are currently grouped by what channel they are in. Each column gives a total sum. I was asked to see if we can combine the total sum into one number, so it shows how many total SKU's are being…