I would like to automate a due date of 5 weeks from the creation date unless the status is “On Hold”. Then the date should be blank. When the status changes from “On Hold” to "Open" then the date can be recalculated as above. Unclear how this can be done.
@Cath Jones
Change the column names to match your column names. Add the formula to your Due Date column - ensure that it is setup as a Date column.
=IF([Status]@row = "Open", [Created]@row + 35, "")
This is giving you a date if status = Open, or blank for any other status.
Hope this help!
Hi all, reaching out to see if of you have ideas; I'm hoping this makes sense: I'm having some trouble getting my formulas to pull data in correctly. I currently have a sheet (primary data) where I have data in rows where each row is a single project, with columns identifying persons, $ values, unique project identifier,…
Hello, I have a workflow where, when a team member checks a checkbox, Smartsheet automatically sends an email to themselves containing merge fields that are used as a customer email draft. The challenge is that this activity typically happens on a deadline day, and a team member may need to generate 30 or more of these…
I have a sheet with 5000 rows and 30 columns. with 4 columns of them are formular columns. How can i reach this limit for 25000000 formular cells reference? How can i enlarge this limit? I need those formular to link some data from another sheet as there is also Max cells limit for one sheet. How can I join those data…