I want to track how long an open task is delayed on a project
Hello,
You might be interested in using the baseline method to track planned vs actuals: https://www.smartsheet.com/blog/quick-guide-mimicking-baseline-functionality-smartsheet
Hi,
By how long you mean:
How much diff there was from the initial due date?
or
If a task is not completed, how much time past from the due date (meaning Today - Due date)?
How long has past since a task is considered delayed (time that past since status was changed to "delayed", etc.)?
or, something else?
Sorry, I was out of the office. I would like to track: If a task is not completed, how much time has past from due date and also track due date changes (the difference between the original due date and new due date) open task only.
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.
I have reproduced the following behavior in a validated Smartsheet application. User permission: Editor (not Admin) Row status: Locked (confirmed via row menu displaying "Unlock Row") Text, Date, Contact List, and Checkbox columns cannot be modified. Dropdown List columns remain editable. Selecting a new dropdown value and…