Hi,
I would like to change a symbol cell based on the status of a predecessor completion status i.e.
"If a predecessor completion status is 100% then the status of this raw should change".
Hi Shanon,
You can do this by creating an IF formula in the symbol column. To get a better sense of how this works, I recommend taking a look at this blog post:
https://www.smartsheet.com/blog/support-tip-automate-RYG-balls
There are also a few posts here in Community with specific examples that you can draw on.
https://community.smartsheet.com/discussion/automate-ryg-project-tasks
https://community.smartsheet.com/discussion/if-and-formula-rgy
Happy formula building!
-Gwyneth
Sorry to be the bearer of bad news, but despite the tutorials/threads linked to above, the answer is no.
There is no way to reference the values in the Predecessors column in any meaningful way.
An IF statement in the Symbol column will only be useful if your tasks are Children of the Predecessor. There is also the added complexity of SS, FS and FF relationships to be considered.
Building nested IF statements with additional identifier columns et. will make a complex web of formulas that will almost certainly fall over in practice.
Kind regards,
Chris McKay
Apologies, I didn't look carefully enough at your request Shanon—it's more complex that my solution solves for. Thanks for chiming in Chris.
Regards,
Gwyneth
Hi all, reaching out to see if of you have ideas; I'm hoping this makes sense: I'm having some trouble getting my formulas to pull data in correctly. I currently have a sheet (primary data) where I have data in rows where each row is a single project, with columns identifying persons, $ values, unique project identifier,…
Hello, I have a workflow where, when a team member checks a checkbox, Smartsheet automatically sends an email to themselves containing merge fields that are used as a customer email draft. The challenge is that this activity typically happens on a deadline day, and a team member may need to generate 30 or more of these…
I have a sheet with 5000 rows and 30 columns. with 4 columns of them are formular columns. How can i reach this limit for 25000000 formular cells reference? How can i enlarge this limit? I need those formular to link some data from another sheet as there is also Max cells limit for one sheet. How can I join those data…