how do i build a formula that gives me the actual date for today + 35 working days?
=Workday(Today(), 39)
will give you 39 working days from today.
https://help.smartsheet.com/function/workday
You need to put that in a date column and you need to understand that the date will change each day you load the sheeet. Today() will always refresh with the current day's date.
Hope that helps!
awesome thanks
You're welcome!
Hi all, reaching out to see if of you have ideas; I'm hoping this makes sense: I'm having some trouble getting my formulas to pull data in correctly. I currently have a sheet (primary data) where I have data in rows where each row is a single project, with columns identifying persons, $ values, unique project identifier,…
Hello, I have a workflow where, when a team member checks a checkbox, Smartsheet automatically sends an email to themselves containing merge fields that are used as a customer email draft. The challenge is that this activity typically happens on a deadline day, and a team member may need to generate 30 or more of these…
I have a sheet with 5000 rows and 30 columns. with 4 columns of them are formular columns. How can i reach this limit for 25000000 formular cells reference? How can i enlarge this limit? I need those formular to link some data from another sheet as there is also Max cells limit for one sheet. How can I join those data…