Hello,
Is there anyway to default dependences so that when you start a new project sheet the dependences are already set? I am currently setting up multiple projects and having to enter working weeks, hours per day and holidays is quite time consuming.
Have you tried creating you baseline project sheet (I deliberately avoid the word "template") and then Save as New when you are ready for the next project?
When I do that, my settings are brought over to the new sheet.
Craig
Cheers Craig, I haven't done that yet, but as I pushed the submit button on my comment that thought did cross my mind and now you have confirmed it I will have to give it a try.
Thanks
Justin