What is the formula to use if I was to populate a value in one column if the Start date is today's date or later? Is this possible? So if the start date is todays date (for example) I would like the status column to change from a value of Planned to Current. Any ideas?
Hi,
Try something like this.
What do you want it to show if there isn't a date?
=IF(Date@row >= TODAY(); "Current"; "Planned")
The same version but with the below changes for your and others convenience.
=IF(Date@row >= TODAY(), "Current", "Planned")
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did it work?
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.
I have reproduced the following behavior in a validated Smartsheet application. User permission: Editor (not Admin) Row status: Locked (confirmed via row menu displaying "Unlock Row") Text, Date, Contact List, and Checkbox columns cannot be modified. Dropdown List columns remain editable. Selecting a new dropdown value and…