I CANT FIGURE THIS OUT!!! - SEND HELP!
I have a "At Risk" Column for this formula
I have a start date / finish date / % complete column
this is what I am trying to automate
Past the due date and not 100% complete (RED).
Less than 60% complete for tasks coming due within 5 business days (YELLOW).
Above 60% complete for tasks coming due within 5 business days (GREEN).