Highlight critical path
I have just started trying to use Smartsheet for project planning. I have created a Gantt chart for my project, and entered dependencies, durations and resources. However, I haven't yet found a way of highlighing the critical path. When managing a project, it is useful to have the tasks and the dependencies that are…
Uncompleted tasks can't start until today
I' ve just started trying to use Smartsheet as a project planning tool. I have created a Gantt chart for my project, and put in the resources. Where tasks are fully or partly completed I have put in the % Complete figure. The system does not seem to have adjusted the start and finish date of tasks that are not 100%…
Does anyone have any great manufacturing process systems
I am always looking for some ways to improve our sheets and the overall system. i run a manufacturing company and I am looking for anyone who is will to share their flow in smartsheet. We do a rebuild every year and do a planning week to refresh our processes. It is time to do this so any shared ideas would be great.
Formula to calculate count of checkboxes in multiple columns and child rows
Hi Everyone, I'm trying to write a formula that adds up the number of unchecked child rows in the Complete column and then subtracts the number of checked rows from the Non Applicable column. The result should be a number of tasks left to be completed from within that parent and child section. I've tried a bunch of…
Automatically send a web form (feedback survey) as part of notification alert or conditional formatt
Is there any way to automatically send a web form (feedback survey) as part of notification alert or conditional formatting? I have a sheet with a web form that customers can use to submit requests for service. This sheet is viewable by staff that it is shared to. I also have a customer service feedback sheet that is not…
Hierarchy in Reports
Is there any intention of offering a hierarchy in the Report view? This would be especially useful where the report includes parents of the items found for the report. Thanks in advance, Neil
Critical Path and Resource Levelling
I just started using Smartsheet for project planning. I have created a lot of tasks, put in the predecessors for each task, put in task durations and put in resources. The resulting plan shows that Person A is doing multiple tasks concurrently. He can't do this. MS Project has a feature which I think is called Resource…
Product Planning Process
Hi community, I', looking after any template that is useable for a Product Planning Process. I'm working in planning, developpment of industry products (Generators, Gensets)....
Web Form Submission Notification
When a web form is submitted, and a record is generatied in my SmartSheet, can I get a notification email containing the Web Form information that was submitted? We have people registering for a conference, and need to know when a new registration is created.
How to link appended cells /row in source sheet to destination sheet
Hi, I have ben able to learn how to link cells from source sheets to destination sheets and observed auto refresh in destination sheetfor teh cells linked already. My query is, if additional cells/rows are appended in source sheets ( quite possible), what is the way to get these also automatically refreshed/refklected in…