-
How to Concatenate multiple cells into a single cell within a VLOOKUP formula?
I've created a VLOOKUP formula to pull in data from a source smartsheet, into a 'staging' smartsheet but, if more than one row match the criteria, only the first row entered in the source smartsheet get entered into the cell on the 'staging' smartsheet. For instance, I'm looking for entries on the source smartsheet that…
-
How to determine how close I am to linking limits
Hi all, Is there a reasonable way to know if I'm getting close to the cross sheet link limits? Thanks, Darrell
-
Trouble with nesting formula, could use some advice
Hello, I am attempting to use nested formula's to create a status update. I started with, =IF(NO(ISBLANK([Date Submitted to Engineering]),"Sent to Engineering")) and it worked fine. The problem is I need to add multiple status options, with automation like this. So I added the second status and it will not work. Here is…
-
Using Sumif within the sum range
I'm trying to sumif my % complete (and eventually average that number) within a summary row in the same column above. I can do this for 1 row, but when I fill the formula down it creates a circular reference and blocks the row above as well. Is it possible to solve this without using a helper column? I've also tried using…
-
SUM or COUNTIF across sheets
I have a Smartsheet for each fiscal year, and will continue to add new sheets for each FY. On a separate sheet, I want to find the sum of values that appears in all of the FY sheets. For example, if I want to sum the total amount an employee makes on my Summary Sheet, referencing data on multiple FY sheets, I know I can…
-
Changing date within formula
I am looking to find a way to incorporate a changing value to the hours needed per day in order to meet deadlines. In addition i've input task completion % in order to account for the completion rate. My current formula is the following : =IF(ISNUMBER([Man Hours Allowed]3), ([Man Hours Allowed]3 / Duration3) * (1 - [%…
-
Adding Month and Days to a Cell
Hello everyone, I have a Completion Date of 1/08/2019 and I need the next cell to be 1/29/2019 (which is ten days before 2/8/2019) and the third cell to be 2/18/2019 (which is ten days after 2/8/2019). I've tried every which way I could think of to get this to work. Any ideas? THANK YOU!
-
Circular Reference Won't Go Away
Hi, I'm working on fairly large sheets that reference many other sheets. My main summary sheet is doing SUMIFS formulas to summarize and sum to a higher level. The summary sheet column is showing a Circular Reference error. I found the error on my raw sheet and corrected. However the main summary file still shows a…
-
Automated Workflows Not Quite There
Hi I wanted to use automation to help update fields in a sheet and that does not work. If I update a field for example When field "With" changes to "Cierr" change the complete column to "Star" This does not work. I have to create a calculation in the cell to reference this. It would be much easier to add automation for the…
-
Create a list based on set of values
Hi there, If, for example, I had a stock list telling me how many of certain T-Shirt sizes I have left vs how many have been ordered. How could I use that to return the sizes, in text form, of those which I don't have enough of. See attached image for example. In this example, I would want to automatically generate a list…