Hello everyone,
I have a Completion Date of 1/08/2019 and I need the next cell to be 1/29/2019 (which is ten days before 2/8/2019) and the third cell to be 2/18/2019 (which is ten days after 2/8/2019). I've tried every which way I could think of to get this to work. Any ideas?
THANK YOU!
Are you using date type columns?
Hi Paul,
Yes I am.
Ok. I asked because your Date Range End column is not showing a date format.
What is the logic you are using to determine the dates? Do you go one month out and then calculate 10 days on either side of that date? Or is it 30 days out, or....?
Hi all, I am trying to build out a formula that will return "True" if the CIF #@row can be found above it in the same column (CIF #) AND the Days Since Created is between 30 - 365 days. All of the formulas I have tried have only gotten me so far as the "AND". Adding in the dates screws it up. The goal is to determine if…
I am getting a lot of REF errors for my predecessors and I can't figure out why. At first I thought I might have REF for predecessors to predecessors but that's not the case. When I export the file into Excel it shows the IDs in the place where it shows REF in SS. Each time I refresh the file I feel like different values…
I am trying to create a sheet summary, where the field is a formula that relies on a contact card within a column. However, it keeps returning a result of "#NO MATCH". The columns involved are, 1:) Priority (symbol column) for Up, Unchanged, and Down, and 2:) Contact Card column. I am trying to get a sheet summary formula…