Hello, has anyone developed an equation for a "health status" (red, yellow, green balls) that considers both the task status in comparison to the planned start/end dates as well as the weight of that task duration?
I tried playing around with the following logic:
Green: the task is not late and the actual % complete of the tasks is greater than or equal to 90% of the planned (aka baselined) % complete.
Yellow: the task is not late and the actual % complete of the tasks is greater than or equal to 75% of the planned (aka baselined) % complete.
This does not really work though, because the difference between a green and yellow status for a task is 3.5% variation between Actual % Complete and Planned % Complete (and my team typically tracks Actual % Complete in 5% increments because no one is going to say a a tasks is 13.5% complete!). Curious if anyone has a create way to showing "Health Status" in relationship to the baseline.
Thanks!