Project Schedule Health from PMO Template
Answers
-
Hi @Marcia562,
Here is a revised version that will have activities that start in the next 10 days turn green:
=IF([% Complete]@row = 1, "Blue", IF([End Date]@row < TODAY(), "Red", IF(AND([Start Date]@row <= TODAY(), ABS(NETWORKDAYS(TODAY(), [Start Date]@row) + 1) / ABS(NETWORKDAYS([Start Date]@row, [End Date]@row)) > [% Complete]@row), "Yellow", IF(AND([Start Date]@row <= TODAY(), ABS(NETWORKDAYS(TODAY(), [Start Date]@row) + 1) / ABS(NETWORKDAYS([Start Date]@row, [End Date]@row)) <= [% Complete]@row), "Green", IF(AND([Start Date]@row > TODAY(), [Start Date]@row <= WORKDAY(TODAY(), 10)), "Green", "")))))
For best practices, please reference Advanced Formula Examples sheet in the Smartsheet Formula Examples Template (Smartsheet Formula Examples Template | Smartsheet).
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.4K Get Help
- 395 Global Discussions
- 213 Industry Talk
- 449 Announcements
- 4.6K Ideas & Feature Requests
- 141 Brandfolder
- 133 Just for fun
- 131 Community Job Board
- 453 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 293 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!