With Dependencies enabled, can End Date be earlier than Start Date?

CPrizzia
ββ
Pretty straight forward... there are scenarios when a task will get done early, sometimes ahead of when it was originally scheduled to begin. Is it possible to have an end date that is earlier than the start date?
Answers
-
No, in theory it's not possible to finish work that hasn't started. Many people use 2 sets of columns for their project plans. 2 columns for Target Start/End Dates, and 2 columns for Actual Start/End dates. That way you can keep track to target and actual dates and even make comparisons if desired.
Technically you can only not have an End Date prior to your Start Date on the date columns defined in your Project Settings.
All the best,
-Ray
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.8K Get Help
- 474 Global Discussions
- 203 Use Cases
- 515 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 82 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives